Installation of a new cedar shake roof to the carriage house building. The Farmstead Alliance partnered with Upper Moreland Township to share the overall cost of the project and to coordinate the work performed by the architect, engineer and building contractor.
Geographies
Not indicated
Dates
Jan 1, 2024 – Dec 31, 2024
Source
990
No causes provided
No populations provided
–
$107K
18th Century Barn Window Restoration
Work in progress project to repair or replace six (6) original 18th century barn windows.
Geographies
Not indicated
Dates
Jan 1, 2024 – Dec 31, 2024
Source
990
No causes provided
No populations provided
–
$1.1K
Emergency Farmhouse Repairs
Emergency repairs to stop rain water leakage into the farmhouse that was entering through the roof and chimney.